SiliciumHex FieldKit

Supply Chain · Make

OEE Improvement Loop

Measure availability, performance and quality on the constraint machine; the biggest of the three losses is your first lever.

  • Time1 h
  • FormatTeam
  • StageMake

OEE Improvement Loop: what it is and why it works

Overall equipment effectiveness (OEE) measures how much of a machine's planned production time actually produces good parts at the ideal rate. It is the product of three factors: availability (run time divided by planned production time), performance (ideal cycle time multiplied by total count, divided by run time) and quality (good count divided by total count). The improvement loop applies the measure where it matters most, on the constraint machine. The team collects a week of shift data, calculates the three factors, identifies which one has the largest loss, and runs a focused improvement on that loss with the operators before measuring again the next week.

Splitting OEE into its three factors turns a single disappointing number into a direction. Low availability points to breakdowns and changeovers, low performance to small stops and reduced speed, and low quality to startup and process rejects; together these are the Six Big Losses of TPM. Working on the constraint first matters because an hour gained there raises plant output, while gains on other machines may only build inventory. Weekly re-measurement keeps the data honest and shows whether a fix holds. The loop links directly to SMED when changeovers dominate availability, to Theory of Constraints for choosing the machine, and to supply kaizen for broader flow improvements.

What you need

  • The constraint machine, identified from queue observation or capacity analysis
  • One week of shift data: planned time, downtime by reason, total count, good count
  • The ideal cycle time or rated speed for the products run
  • Operators and maintenance technicians available for a focused improvement session

What you get

  • Availability, performance, quality and OEE for the week
  • Losses broken down by the Six Big Losses categories
  • One targeted improvement action on the largest loss, with an owner
  • A weekly OEE trend to check whether the improvement holds

When to use it

When the line is busy all day yet output does not follow.

How to do it, step by step

  1. Pick the constraint machine and collect shift data.
  2. Compute availability, performance and quality for one week.
  3. Find the largest of the three losses — that is the lever.
  4. Run a focused improvement on that loss with the operators.
  5. Re-measure weekly; an OEE that is not re-measured is a rumor.

Worked example: Raising output on a lubricant filling line

Illustrative scenario — figures are realistic but not from a real company.

A lubricant blending plant filled quart and gallon bottles on one high-speed filling line that limited shipments. The line was scheduled 6,000 minutes a week and was rated at 60 bottles per minute. Customers faced back orders despite overtime.

  1. The team logged one week of data. Downtime totaled 1,500 minutes, of which 900 were product and bottle-size changeovers and 600 were breakdowns and jams, giving availability of 75%.
  2. The line produced 243,000 bottles in 4,500 minutes of run time against an ideal of 270,000, so performance was 90%. Of these, 238,000 were good, giving quality of about 98%.
  3. OEE came to roughly 66%. Availability was by far the largest loss, and changeovers were its biggest component.
  4. Operators and a mechanic ran a focused improvement on changeovers: pre-staging caps and labels, marking guide rail positions for each bottle size, and moving line flushing to a standard sequence.

Result. Changeover time per week fell from 900 to about 450 minutes, lifting availability to around 82% and OEE to roughly 73%. Back orders cleared within a month. The team then turned to jams, the next biggest loss, and kept the weekly OEE review on the line's board.

Common pitfalls and how to avoid them

  • Improving OEE on every machine at once, including those with spare capacity.Start with the constraint, where each gained hour increases total output.
  • Excluding changeovers or small stops from downtime to make the numbers look better.Define planned production time and loss categories clearly, and record all stops that occur during planned time.
  • Using a conservative ideal cycle time, which inflates performance.Use the machine's rated or best demonstrated speed for each product as the ideal.
  • Comparing OEE across plants or machines with different definitions.Use OEE mainly to track improvement on the same machine over time, with stable definitions.

Frequently asked questions

How do you calculate OEE?

OEE equals availability times performance times quality. Availability is run time divided by planned production time. Performance is ideal cycle time multiplied by total count, divided by run time. Quality is good count divided by total count. An equivalent shortcut is good count times ideal cycle time, divided by planned production time, which shows OEE as the share of planned time spent making good parts at full speed.

What are the Six Big Losses in OEE?

They are breakdowns and setups or adjustments, which reduce availability; small stops and reduced speed, which reduce performance; and startup rejects and production rejects, which reduce quality. The categories come from Total Productive Maintenance and help teams classify losses so they can target the largest one.

What is a good OEE score?

An often-quoted benchmark is 85% for discrete manufacturing, but it is a rule of thumb rather than a standard, and achievable levels depend on the process, product mix and how losses are defined. Continuous process lines and high-mix job shops differ widely. It is more useful to compare a machine against its own baseline and track improvement than to chase a universal target.

Origin

OEE — Seiichi Nakajima, TPM, 1970s.

Related methods

More in “Make”

Turn materials into products at the constraint’s rhythm.